American Water Heater American Water Heaters Residential Gas Water Heater Water Heater User Manual


 
23
INSTALLATION OF VENT SYSTEM, SIDEWALL
With the route of the venting system and selection of materials completed,
as discussed in the section of this manual titled PLANNING THE VENT
SYSTEM,thethroughthewallventterminalinplaceandtherstsection
ofpiping,uptorstelbow,installedatthebloweritistimetocompletethe
installation of the venting system for the sidewall installation.
FIGURE 20
It is recommended that the completion of the venting system start
at the blower assembly and run to the coupling on the inside wall
of the vent terminal, Figure18.
Theventsystempipingshouldbesupportedevery5feet(1.5m)
ofverticalrunandevery3feet(91cm)ofhorizontalrun.Followvent
pipemanufacturer’sinstructionsforproperjoiningprocedures.
Ifnecessarytoachievethe12”minimumclearanceabove
the highest anticipated snow level, install a snorkel as shown
in bottom portion of Figure 20.
NOTE: With the installation of a snorkel it is necessary to
usetwo90°elbowsthatshallbeconsideredalongwiththe
additional vent pipe when calculating maximum equivalent
feet of venting.
INSTALLATION OF VERTICAL VENT SYSTEM
Aproperflashingor“BOOT”shouldbeusedtosealthe
pipe where it exits the roof. The total vent system should
not exceed the equivalent feet of pipe as listed in Table 2.
Provide support for all pipe protruding through the roof. All piping should
be properly secured. The vent system piping should be supported
every5feet(1.5m)ofverticalrunandevery3feet(91cm)of
horizontalrun.Followventpipemanufacturer’sinstructionsforproper
joining procedures.
FIGURE 21
IMPORTANT
The vent system must terminate so that proper clearances
are maintained as cited in local codes or the current edition
oftheNationalFuelGasCode(ANSIZ223.1)ortheNatural
GasandPropaneInstallationCode(CAN/CSA-B149.1)andas
listed below:
1. VentTerminationmustextendaminimumof12inches(30cm)
aboveroofor12inches(30cm)abovetheanticipatedsnowlevel
to prevent blockage of the vent termination, as shown in Figures
20 and 21.