14 E33 FPI Direct Vent Gas Insert
INSTALLATION
Diagram 5
11) Push the FPI logo plate into the two holes
in the bottom left corner of the faceplate.
The standard fl ush door comes with a black
frame. To install the frame, simply hook the top
door fl ange onto the top of the unit and swing
the door towards the unit, (Diagram 1 and 2).
Be careful that the glass gasket does not roll up;
there must be a gap between the gasket and
the door lip to ensure that the door sits securely
on the unit. Refer to Diagram 3.
10) Attach the faceplate panels to the insert
body using the 4 remaining black screws.
Refer to Diagram 5.
STANDARD
FLUSH DOOR
Diagram 3
Secure door by fastening with two screws located
at bottom of glass frame (refer to Diagram 1).
Diagram 2
To remove the fl ush door, reverse the above
steps.
FLUSH LOUVERS
2) Install the Spring Hinges on the left and right
side of the bottom of the Firebox using 2
screws per hinge.
3) Place the Bottom Louver near the hinge. Flip
hinge over the Bottom Louver and secure
using 3 screws.
Bottom Louver
Hinge
Location
1) The top louver is held in place by friction fi t.
Refer to Diagram 1
Diagram 1
4) Install the Top Frame by hooking it onto the
two screws at the top of the full screen door.
It is held in place by magnets.
Top Frame
Screw
1) Hold the full screen faceplate up against
the unit in order to make the following wire
connections.
Pull the ON/OFF connector wires thru the
box and connect them to the switch.
Connect the fan switch wires with the wire
connectors from the fan speed control. Place
clips over wires and tuck into side trim.
FULL SCREEN FRONT
2) Lift the unit up slightly and push down on
the corners of the Bottom Trim Bracket and
slide under unit.
3) Completely secure faceplate to the unit by
securing 4 screws to the Left and Right Side
Trim.
Bottom Trim
Bracket
Push in Corners
Screws