8 E33 FPI Direct Vent Gas Insert
VENTING
THE APPLIANCE MUST NOT BE
CONNECTED TO A CHIMNEY FLUE
SERVING A SEPARATE SOLID FUEL
BURNING APPLIANCE.
This appliance is designed to be attached to
two 3" (76mm) co-linear aluminium fl ex running
the full length of the chimney. The fl ue length
must be a minimum length of 8 ' (2.44m) and
a maximum of 35' (10.7m). See chart above
for minimum distances from roof. Periodically
check that the vent is unrestricted.
Masonry chimneys may take various contours
which the fl exible liner will accommodate.
However, keep the fl exible liner as straight
as possible, avoid unnecessary bending.
Part # Description
948-305 3" Flex - 35 ft.
946-529 FPI Co-linear DV Vertical
Termination Cap
Alternate Approved Caps
980 Vertical Termination Cap
991 High Wind Cap
923GK 3" Co-linear Adaptor with
ashing
GAS CONNECTION
GAS CONNECTION WARNING:
Only persons licensed to work
with gas piping may make the
necessary gas connections to
this appliance.
1) If the appliance is to be installed into an
existing chimney system, thoroughly clean
the masonry or factory built fi replace.
2) The appliance is provided with an opening
on the left hand side of the control compart-
ment. A 3/8" NPT gas supply pipe must be
brought near this inlet hole.
In areas of consistently high winds, we recom-
mend using the Simpson Dura-Vent System
(923GK adapter and 991 high-wind cap).
The Air Intake pipe must be attached to the inlet
air collar of the termination cap.
INSTALLATION
3) Locate the center point where the vent will
pass through the chimney above the ap-
pliance. Move the appliance into the exact
location where it is to be installed. Ensure
that the Insert is level.
FLUE LINER
INSTALLATION
1) Cut the fl ex liner as required.
2) Mark the end of one liner to indicate
Exhaust.
3) Connect the other end of the above liner to
the exhaust side of the termination adap-
tor, seal connection with high temperature
silicone. Secure with gear clamp.
4) Connect the 2nd liner to the inlet side of the
adaptor, seal connection with high tempera-
ture silicone. Secure with gear clamp.
5) Install ashing.
6) Insert both liners into chimney, passing
through the damper opening.
7) Install termination cap.
8) Connect the marked end of the liner to the
exhaust collar of the vent connector plate
marked with an "E", seal connection with
high temperature silicone. Secure with gear
clamp.
9) Connect the 2nd liner to the intake collar, seal
connection with high temperature silicone.
Secure with gear clamp.
NOTE:
1) Final gas connection should be made after
unit is in place to avoid damage to line when
pushing the unit into position.
2) Mill-pac may be used instead of high
tempture silicone and screws may be used
instead of gear clamps at connections of
liner to inlet and vent collars.
10) Align vent connector plate with guides on
unit.
11) Slide unit into masonry opening, while ensur-
ing that the slot at the rear of the connector
plate mates up with the hold down plate on
the unit.
12) Secure with Screw.