All Linear series boilers are shipped either as an assembled boiler block or a knock-down
boiler block. If the block came unassembled, or if the assembled block needs to be split for installa-
tion purposes, please read the following:
To assemble split blocks, move the sections into a line facing each other. Sections may be slid
along boards placed underneath the sections. Inspect nipple ports for damage or burrs. Remove any
burrs by brushing the port very lightly. Wipe the push nipples and nipple ports with a clean cloth.
Apply a film of nipple compound to both the nipple and port. Install the nipple in the port and then
seal it by hitting it with a rubber mallet. Apply section sealant to one section only and slide sections
together. If the boiler came in sections, you will want to draw the sections together 2 or three at a time
to insure that the blocks are coming together properly. Install the four draw rods and draw the sections
together evenly (measure with yardstick). The longer draw rods should be installed on the top of the
boiler. The shorter draw rods are installed on the bottom of the boiler. The bottom draw rods should
not extend past the front section. Draw the sections together until sections make iron-to-iron contact
at a point around the top and bottom ports of each section. Check to insure that the combustion cham-
ber is sealed using a flash light or other lighting device. Place the flashlight into the combustion
chamber and look for light on the floor or surrounding walls (this is best done in a dark room). If light
appears out of the boiler use a high temperature caulk to fill in the gaps between the block sections.
DO NOT OVER TIGHTEN DRAW RODS
6. Boiler Block Assembly:
The BIASI B-40 Boiler Trim Kit includes the following components.
The above mechanical components should be installed following the diagram of the boiler
tappings on the following page. The installation of the above wiring components (wiring harness) will
be described in the wiring portion of this installation manual.
7. Installation of Boiler Trim Components:
1— Honeywell L4006 E Aquastat
1— 3/4” X 3” Nipple
1— 3/4” Elbow
1— 50 PSI Pressure Relief Valve
1— Immersion Well
1— Four Wire Molex Wire Harness
1— Pressure/Temperature Gauge
1— 3/4” Boiler Drain
1— 1/4”X3/4” Bushing
1— 2 1/2” MPT Supply Manifold
1— 2 1/2” MPT Return Manifold