Heat & Glo LifeStyle COSMO-I35 Boiler User Manual


 
Heat & Glo • Cosmo-I30, Cosmo-I35 • 2239-900 Rev. H • 1/11 28
11
11
Finishing
A. Mantel and Wall Projections
WARNING! Risk of Fire! Comply with all minimum clear-
ances to combustibles as speci ed. Framing or nishing
material closer than the minimums listed must be construct-
ed entirely of noncombustible materials (i.e., steel studs,
concrete board, etc).
Clearance to combustible material under the insert is 1/4
inch (6 mm). Clearance from top of replace opening for
combustibles extending 12 inches max. is 12 inches.
Use leveling legs to raise insert minimum 1/4 inch (6 mm)
above combustible material or outer wrap of factory built
rebox.
Combustible facings must not extend behind the insert
surround. For non-combustible material speci cations
refer to section 1.E.
Figure 11.1 Clearances to Mantels or other Combustibles
above Appliance
12 IN. MIN.
12 IN. MAX.
EXISTING NON-COMBUSTIBLE FACING