16 Installation (for qualified installers only)
Travis Industries 4122104 93508117
Termination Requirements (see the illustration below)
A Minimum 9" clearance from any door or window
B Minimum 12" above any grade, veranda, porch, deck or balcony
C Minimum 12" from outside corner walls
D Minimum 12" from inside corner walls
E Minimum 11" clearance below unventilated soffits or roof surfaces
Minimum 18" clearance below ventilated soffits
Minimum 6" clearance from roof eaves
NOTE: Vinyl surfaces require 24"
11 Min.
6 Min.
Roof
Surface
Roof
Eaves
F Minimum 18" clearance below a veranda, porch, deck or balcony (must have two open sides)
G Minimum 48" clearance from any adjacent building
H Minimum 84" clearance above any grade when adjacent to public walkways or driveways
NOTE: may not be used over a walkway or driveway shared by an adjacent building
I Minimum 48" clearance from any mechanical air supply inlet, 72" for Canada
J Minimum 36" clearance above and 48 below and to the sides of non-mechanical air supply inlet
K Minimum 36" from the area above the meter/regulator (vent outlet)
L Minimum 36" from the meter/regulator (vent outlet)
M Minimum 12 above the roof line (for vertical terminations)
N Minimum 24 horizontal clearance to any surface (such as an exterior wall) for vertical terminations
C
B
H
E
G
A
D
F
L
K
J
I
NOTE: Measure clearances to the nearest edge of the exhaust hood.
A
E
E
M
N
Use the vinyl siding standoff (#950) when installing on an exterior with vinyl siding.
Vent termination must not be located where it will become plugged by snow or other material
These clearances meet UMC-1994 and the CNA/CGA-B149 code standards.