Installation
Pre-Startup
Requirements
Pre-Startup Checklist
Complete this checklist after installing the
unit to verify all recommended
installation procedures are complete
before unit startup. This does not replace
the detailed instructions in the
appropriate sections of this manual.
Always read the entire section carefully
to become familiar with the procedures.
WARNING
Hazardous voltage!
Disconnect all electric power,
including remote disconnects before
servicing. Follow proper lockout/
tagout procedures to ensure the
power can not be inadvertently
energized. Failure to disconnect
power before servicing could result in
death or serious injury.
Receiving
Inspect unit and components for
shipping damage. File damage claims
immediately with the delivering carrier.
Check nameplate unit data so that it
matches the sales order requirements.
Check unit for missing material. Look
for ship-with accessories that are
packaged separately and placed inside
the access panel, fan section, or
compressor section. See the
“Receiving and Handling” section on
page 6.
Unit Location
Ensure the unit location is adequate for
unit dimensions, ductwork, piping, and
electrical connections.
Ensure access and maintenance
clearances around the unit are
adequate. See the “Service Access”
section on page 7.
Unit Mounting
Remove shipping brackets on the
compressor assembly and supply fan.
Component Overview
Verify the fan and motor sheaves are
aligned.
Check the belt tension for proper
adjustment.
Ensure the fan rotates freely.
Tighten locking screws, bearing set
screws and sheaves.
Ensure bearing locking collars do not
wobble when rotated.
Ensure all air filters are properly
installed with consideration of size and
air flow.
Manually rotate the condenser and
evaporator fans to ensure free
movement. Verify that all of the fan
mounting hardware is tight.
Ductwork
Verify that all ductwork conforms to
NFPA 90A or 90B and all applicable
local codes.