GE 7500 SERIES Air Conditioner User Manual


 
BUILD AND INSTALL THE
ZONELINE BASE PLATFORM
1. Construct a 23
1
4min. x 23
1
4min. square platform.
NOTE: The platform must have a load-bearing
capacity of 175 lbs. minimum.
1
Installation Instructions
18
WALL PLENUM AND ARCHITECTURAL LOUVER INSTALLATION
• Install the appropriate wall plenum through the exterior wall in accordance with the Installation Instructions
provided with the plenum.
IMPORTANT: The wall plenum is not designed to carry structural loads.
Proper wall header construction is required. The plenum requires proper
flashing, shim and caulk for a weather resistant installation.
Properly square and
level plenum.
Proper header for
structural support.
Apply proper caulking
and flashing.
Architectural
Louver—RAVAL1
Exterior/Outside Wall
Case
Wall Plenum
RAVWP6 – 6D x 19
3
4W x 32H
RAVWP8 – 8D x 19
3
4W x 32H
RAVWP12 – 12D x 19
3
4W x 32H
RAVWP15 – 15D x 19
3
4W x 32H
2. Place the platform in the utility closet with the
following clearance between it and the interior
surface of the walls/door/panel:
4 min. from front of the case – Unit to be
installed through FRONT of case
5 min. from front of the case – Unit to be
installed through SIDE of case
3 min. from two sides of the case
3. Align the platform with the opening of
the wall plenum and secure to the floor
using appropriate brackets and bolts.
23
1
4min.
23
1
4min.
8min.
for drain
access
Cutout for drain
connection