1. COMMISSIONING
1.1 Close all openable doors and windows in the room, ignite
the stove and operate on maximum for 10 minutes. Position
a lighted smoke match just inside the draught diverter
opening and check that all smoke is drawn into the opening.
See diagram 1. If there is any doubt, run the stove for a
further 10 minutes and repeat the test.
1.2 If there are any extractor fans in adjacent rooms, the test
must be repeated with the fans running on maximum and
interconnecting doors open.
IF SPILLAGE PERSISTS, DISCONNECT THE
APPLIANCE AND SEEK EXPERT ADVICE.
For future reference record the installation details on the
commissioning sheet at the end of the User Section of these
instructions.
14
INSTALLATION INSTRUCTIONS
COMMISSIONING
AR1493
1