6.0 Install Termination
6.1 Slide the termination body onto the cable and remove core. Make sure the termination body (not the core) is butted
up to the edge of the vinyl tape marker previously applied (Figure 7). Pull the core while unwinding, counter-
clockwise, starting with the loose end (Figure 7). Be sure to alternate the pulling and unwinding actions (pull-
unwind-pull-unwind-etc.) to help prevent the core material from binding up as the core is being removed.
NOTE: Once the termination body makes contact over the mastic seal area, there is no need to continue supporting the
assembly. DO NOT PUSH OR PULL ON THE TERMINATION ASSEMBLY WHILE UNWINDING THE CORE.
Vinyl Tape Marker
Counterclockwise
NOTE: The material being removed at this step is mixed polymers
and can be recycled.
Figure 7
6.2 Connect ground braid to system ground according to standard practice.
Semi-Con Insulation Shield
Ridge at End of Cable
Insulation Shield (Semi-Con)
Ridge at End
of High-K Tube
Correct Installation of Termination on Tape Shielded Cable
Cable Insulation
Conductor
Vinyl Tape
Marker
Environmental Top
Seal
Stress Controlling Compound
High-K Stress
Relief Tube