Avoid running the Ventura system if the vessel is in contaminated water, such as in a harbor
or canal. The system should be fully tested before leaving port. If the location or weather
prevents proper testing refer to the section “Dry Testing.”
Warning! Damage may occur if the purge sequence is bypassed and the membrane is
pressurized with storage chemical in it.
• Thru-hull inlet valve is open and the brine discharge valve is open.
• All of your hose connections are tight.
• The green tag with the spacer under the pressre relief valve has been removed.
• The pressure relief valve is open 1/2 turn.
• The switch on the MPC control box is set to the“Auto” position.
First check that:
Ventura MPC New System Start-Up and Testing
Open 1/2 Turn when Purging Chemicals! Remove Tag and Washer!
Power up the system by turning on the cir-
cuit breaker. A message on the display will
read Open Pressure Relief Valve Now
Push the “Auto Run” Button. The feed
pump will start and the message
“Purging Storage Solution” will appear.
Note: See Part 2 for instructions on dimming the display and programming from the display