Sigma S2Ba Heat Pump User Manual


 
Page 32
ProMinent
®
Dulcodes UV-Desinfektionsanlage
NOTE
The tightening torque of the liquid end screws should be rechecked after 24 hours of
operation.
The tightening torques of the liquid end screws should be checked every 3 months for the
PVT material version.
Start-up/Maintenance
Fig. 13
approx. 300 g
Brass rod 9 mm diam. x approx. 200 mm
Fig. 12
GUIDELINE ON VALVE INSTALLATION
In the case of suction problems during installation, place the valves on a firm surface and tap the
PTFE ball seat disk lightly with a brass rod and a hammer weighing about 300 g. Let the valves
operate in the wet state.
NOTE
If suction problems with the pump or leakage at the overcurrent valve are encountered,
first clean the ball and the ball seat disc.
For media containing particles larger than 0.3 mm it is absolutely essential to install a
filter in the suction line.