3.4) REPLACING GLASS GAUGE & RUBBER WASHERS OR
GLASS PACKINGS (Continued)
The Sight Glass (#10) gives the operator the ability to easily monitor the actual water level inside the
chamber. If the Sight Glass (#10) gets clogged or is no longer functional, it can be very difficult to
troubleshoot a problem.
3.4.2) BRASS SIGHT GLASS (SEISMIC)
GLASS GAUGE and GLASS PACKINGS MUST be
replaced EVERY SIX MONTHS
The Seismic Sight Glass is equipped with BALL
CHECKS in each GAUGE FITTING.
INSTALLATION:
Only properly trained personnel should install and
maintain water gauge glass and connections. Remember
to wear safety gloves and glasses during installation.
Before installing, make sure all parts are free of chips
and debris.
1. Uninstall GUARD RODS, GLASS GAUGE, and GLASS
PACKINGS. (You may need to rotate one of the GAUGE
FITTINGS to remove GLASS GAUGE)
2. Slip a new GLASS PACKINGS on the new GLASS
GAUGE about an inch from the bottom.
3. Now slip the following items through the top of GLASS
GAUGE in the following order:
PACKING GLAND (facing down)
GLASS PACKING NUT (facing down)
GLASS PACKING NUT (facing up)
PACKING GLAND (facing up)
GLASS PACKINGS (inch down from top)
PACKING WASHER
4. Gently insert GLASS GAUGE into GAUGE FITTINGS.
You may need to rotate GAUGE FITTINGS until
vertically aligned, after GLASS GAUGE is in.
5. Carefully raise GLASS GAUGE about 1/16” from bottom
and slide lower GLASS PACKINGS down until it makes
contact with the BOTTOM GAUGE FITTING. (DO NOT
allow GLASS GAUGE to remain in contact with any
metal)
6. Carefully slide upper GLASS PACKINGS up as far as
possible.
7. Hand tighten both GLASS PACKING NUTS, then tighten
1/2 turn more by wrench. Tighten only enough to prevent
leakage. DO NOT OVER TIGHTEN! If any leakage
should occur, tighten slightly, a quarter turn at a time,
checking for leakage after each turn.
8. Reinstall GUARD RODS.