Assembly
Boiler Kit Materials: (Refer to pages 4 & 5)
List of items contained within the boiler kit shipped with the
unit.
1 - Control board cover
1 - Access cover (Hopper Swing Plate Knob)
5 - Spring Handles
1 - 1/2” Boiler Drain
1 - 3/4” Safety Relief Valve
1 - 1/2” Aquastat Well
1 - 1/2” Dual Temperature/Pressure Gauge
1 - 100ft. Sensor Cable (Outdoor Air Sensor)
1 - Outdoor Air Sensor
1 - Flue Tunnel Weldment
1 - Combustion Blower Assembly
1 - Heat Shield (Comb. Blower)
2 - UY Connectors
2 - Terminals 1/4 Female
1 - #8 X 1/2” TEK
3 - 1/4-20 X 5/8” Wing Screw
4 - 1/4” Lock Washer
4 - 1/4-20 Nuts
Installation of the Flue Tunnel Weldment,
Combustion Blower and Wiring, ESP and Heat
Shield:
Step 1: First install the flue tunnel weldment by aligning
the (4) studs up with the (4) holes in the ash
chamber base.Fasten the (4) nuts and lock washers
provided, to the studs by removing the access cover on
the secondary ash chamber.
Step 2: Place the combustion motor onto the flue tunnel
weldment and tighten the (3) wing screws provided.
Step 3: Insert the Exhaust Sensing Probe (ESP) into
the 1/8" hole provided on the flue pipe stub. Fasten
with the (1) #8x1/2" TEK screw also provided. ESP
will be taped to the sheet metal jacket for shipping
purposes.
Step 4: Connect the flex conduit 90 degree elbow(Not
Shown) to the heat shield in the hole provided. Then
connect the (3) wires from the combustion blower with
the (3) wires in the flex conduit by using the push-on
connectors and matching the wire colors as follows:
Red to Black, White to White and Green to Green.
Step 5: Place Heat Shield over combustion blower and
align the swell latches with the holes in the sheet metal
and tighten.