Desa VSGF33PR Indoor Fireplace User Manual


 
107172
14
For more information, visit www.desatech.com
For more information, visit www.desatech.com
Figure 23 - Checking Gas Joints for Propane/LP Gas
Propane/LP
Supply
Tank
Equipment
Shutoff Valve
Gas Control Valve
Gas Meter
Figure 22 - Checking Gas Joints for Natural Gas
Gas Control Valve
INSTALLATION
Continued
INSTALLATION
Checking Gas Connections (Cont.)
Installing Logs
WARNING: You must operate this fireplace with
the fireplace screen in place. Make sure fireplace
screen is in place before running fireplace.
WARNING: Failure to position the parts in accor-
dance with these diagrams or failure to use only parts
specifically approved with this heater may result in
property damage or personal injury.
Each log is marked with a number. These numbers will help you
identify the log when installing. It is very important to install these
logs exactly as instructed. Do not modify logs. Only use logs
supplied with heater.
INSTALLING LOGS
CAUTION: Do not remove the metal data plates
attached to the heater base assembly. The data plates
contain important safety and warranty information.
1. Place front log (#1) on top of the grate. Make sure the notches
in the bottom of the log fit over the grate prongs (see Figure
24). Push back of log flush with metal grate bar.
2. Rest middle log (#2) behind metal posts on front burner. Make
sure the grooves in the bottom of the log fit over the grate.
Bring the log forward next to the metal posts (see Figure 25).
3. Slide the grooves in the back of the rear log (#3) against the
rear grate prongs. Make sure the peg on the log is on top (see
Figure 26).
4. Place the crossover log (#4) on the rear log and the middle log.
Make sure the peg on the rear log is in the hole in the bottom
of the crossover log. The crossover log should fit in the cutout
of the middle log (see Figure 27).
5. Install fireplace screen by slipping notches of fireplace screen
over screws on front of fireplace (see Figure 28, page 15).
Figure 24 - Installing Front
Log (#1)
Figure 26 - Installing Rear
Log (#3)
Figure 25 - Installing Middle
Log (#2)
Middle Log (#2)
Rear Log
(#3)
Peg
Grate
Prong
Rear
Burner
Groove
in Back
of Log
Groove
in Back
of Log
Grate
Prongs
Metal Grate Bar
Front Log (#1)
Notch
Metal Post
Metal
Post
Groove
Groove
Grate
Grate
Prong
Figure 27 - Installing Crossover
Log (#4)
Crossover
Log (#4)
Hole
Peg
Cutout
Equipment
Shutoff
Valve