Chief Manufacturing CM2 Indoor Furnishings User Manual


 
CM2 Installation Instructions
10
Cable Installation and Routing
The CM2 has an integrated cable management system that
allows cables to be automatically "fed out" as the lift raises, and
"reeled in" as the lift lowers while maintaining constant cable
tension.
IMPORTANT ! : The CM2 requires minimum cable lengths of
8 feet from display through lower mount.
To install cables:
1. Remove two screws securing cable guide side cover.
2. Set screws aside for reuse. (See figure 17)
Figure 17
3. Slide cable guide side cover away from mount and carefully
set aside.
Figure 18
4. Loosen six cable clamps. (See figure 19)
5. Route cable(s) down through upper cable clamp.
(See figure 19) and (See figure 20)
IMPORTANT ! : Leave enough cable length available above
upper cable clamp to allow the routing and tie-down of cables
between upper cable clamp and display.
x2
1
Cable Guide
Side Cover
Cable Guide
Side Cover
3