7
THE BOILER IS TOP-HEAVY. Do not
allow it to tip over.
1. Remove the sleeve.
2. Remove the contents from the skid, except
the boiler.
3. Remove the four (4) hex-drive lag screws
holding the boiler to the skid (Figure 1-a).
1. UNPACK THE CRATE
4. Tip the boiler and shimmy it off the skid.
2. POSITION THE BOILER
WARNINGS
1. Slide the boiler into desired location.
2. Meet the minimum clearances to
combustible construction per the
Specification Section of this manual.
OBSERVE MINIMUM CLEARANCES to
combustible walls and ceilings to avoid potential
re hazard.
DO NOT INSTALL ON CARPET. This may cause
a re.
INSTALLING THE BOILER NEAR A SOURCE OF
FLAMMABLE LIQUIDS or gases may cause re or
explosion.
CLEAN BURNERS DAILY if operating the boiler in
a dusty environment.
PROTECT IGNITION SYSTEM COMPONENTS
from sources of water that may spray, drip, or rain
on them during installation or service.
3. Allow 24" service clearance in front and on
the left side of the boiler.
4. Level the boiler, using shims as necessary.
1-b
1-a