Part Number 550-110-268/0699
8
GOLD GV Water boiler — Series 3
Weil-McLain
500 Blaine Street
Michigan City, IN 46360-2388
http://www.weil-mclain.com
Installation — assembly continued
Finish the vent
installation
Figure 11
Installation of condensate tubing
Sealant recommended by vent pipe manufacturer must be used as indicated
in their instructions. Vent and combustion air connector piping must be
sealed gas-tight to prevent possibility of flue gas spillage and carbon
monoxide emissions, resulting in severe personal injury or death.
1. See Figure 11 to install condensate tubing
(provided by others). Use condensate pump
if floor drain is higher than condensate drain
on boiler.
If required:
• use a low-profile pump — OR —
• set boiler on foundation (see
GV Series
3 Boiler Manual
) to allow gravity flow
to pump.
2. Size pump in gal/hr. (boiler model):
• 0.78 (GV-3)
• 1.17 (GV-4)
• 1.56 (GV-5)
• 1.95 (GV-6)
Refer to pump manufacturer's instructions.
Drain to a non-freezing area.
Installing condensate tubing
If vent pipe or combustion air pipe must be reassembled
When vent pipe or combustion air pipe is disconnected for any reason, it must be reassembled
and resealed according to this Venting Supplement, the direct vent termination kit instructions
and the vent pipe manufacturer's instructions.
26806
StaR-34
vent starter tee
5/8" O.D. tubing,
provided by
others
Vent