Pre-installation wiring notes
BMTK-SVN01D-EN 69
®
Pre-installation wiring notes
The wiring for the Tracker system will have been completed prior to
Tracker installation. All Tracker wiring conforms to the following
guidelines:
• The Tracker controller receives 24 Vac from a dedicated power circuit.
If not, the Tracker controller may malfunction.
• Each UCM receives 24 Vac from a dedicated power source. If not, the
UCM may malfunction.
• Input wires and ac power wires are run in separate conduits or wire
bundles. If not, the Tracker controller may malfunction due to
induced electrical noise.
• Comm5 cable and ac power wires are run in separate conduits or wire
bundles. If not, the Tracker controller may malfunction due to
induced electrical noise.
• UCM communication cables do not run near lighting ballasts or other
transformers. If they do, the UCM may malfunction due to induced
electrical noise.