Toshiba RAV-SM2802DT-E Air Conditioner User Manual


 
– 35 –
Concealed Duct High Static Pressure
Installation Manual
10 TEST RUN
Before test run
Before turning on the power supply, carry out the following
procedure.
1) Using 500V-megger, check that resistance of 1M:
or more exists between the terminal block 1 to 3 and
the earth (grounding).
If resistance of less than 1M: is detected, do not run
the unit.
2) Check the valve of the outdoor unit being opened
fully.
To protect the compressor at activation time, leave power-
ON for 12 hours or more before operating.
Execute a test run
Using the wired remote controller, operate the unit as usual.
For the procedure of the operation, refer to the attached
Owner’s Manual.
A forced test run can be executed in the following procedure
even if the operation stops by thermostat-OFF.
In order to prevent a serial operation, the forced test run is
released after 60 minutes have passed and returns to the
usual operation.
CAUTION
Do not use the forced test run for cases other than the
test run because it applies an excessive load to the
devices.
Procedure 1
Keep button pushed for 4 seconds or more. [TEST] is
displayed on the display part and the selection of mode in the
test mode is permitted.
Procedure 2
Push button.
Procedure 3
Using button, select the operation mode, [Cool] or
[Heat].
Do not run the air conditioner in a mode other than [Cool]
or [Heat].
The temperature controlling function does not work during
test run.
The detection of error is performed as usual.
Procedure 4
After the test run, push button to stop a test run.
(Display part is same as procedure 1.)
Procedure 5
Push check button to cancel (release from) the test run
mode.
([TEST] disappears on the display and the status returns to a
normal.)
2, 4
3
1,5
35-EN