11EcoBreeze System Installation
Service access
Install a service platform (not supplied) to facilitate maintenance activities. Regular
maintenance activities require a of minimum 1219 mm (48 in.) clearance on all sides to
remove, maneuver, and install Modules and components.
N
OTE: Consider local soil conditions, codes, and loading when determining appropriate
support footings.
To prevent short cycling of outdoor air, each EcoBreeze Frame must have a minimum of 1219
mm (48 in.) clearance on each side, totaling 2438 mm (96 in.) between Frames, and 1219 mm
(48 in.) at the end of the Frame.
na3526a
1219 (48)
1219 (48)
1219 (48) 1219 (48)
1219 (48)
2438 (96)
1219 (48) 1219 (48)
na3677a
WALL OR OTHER OBSTRUCTION
* Dimensions are shown in millimeters with inches in parentheses.