11.2.5 External Controls
External controls may include time switch, interlock
switch, room thermostat and frost thermostat.
Operate each control to ensure that they function
correctly. Set the switches (if fitted) and
thermostat(s) to the users’ requirements.
11.3 Complete the Start-Up
Ensure that all covers are fitted correctly and all test
points are properly sealed.
11.3.1 Instruction to the User
Explain the controls of the heater to the user
including how to turn it on and off, using the controls
fitted on site.
Give this manual to the user.
Ensure that the user is shown and understands the
importance of maintaining clearances to
combustibles on Page 7, Figure 4, installer
responsibility on Page 6, Section 3 and user
instructions on Page 31, Section 12 and all
warnings defined in this manual.