12 Stove Installation (for qualified installers only)
© Travis Industries 100-01179 4060926
Chimney Termination Requirements
• Must have an approved cap (to prevent water from entering)
• Must not be located where it will become plugged by snow or other material
• Must terminate at least 3' above the roof and at least 2' above any portion of the roof within 10' (see
Figure 6)
Slanted Roofs
F
lat Roofs
Chimney must
extend 3'
above the roof
Chimney must extend 2'
above any portion of the roof
within 10' of the chimney
Chimney must
extend 3'
above the roof
Chimney must extend 2'
above any portion of the roof
within 10' of the chimney
Figure 6
Outside Air Requirements
• Required for mobile homes & in certain localities (check with building officials)
• Must not be drawn from an enclosed space (garage, unventilated crawl space)
• Requires the optional outside air connector or pedestal.
Outside Air
Connector
Outside air entrance must be placed so
it does not become blocked by snow.
When using outside air, find a location where the chimney and
outside air hole do not interfere with structural members of the home.
Pedestal may be used to
direct air from below the
stove. See the pedestal
instructions for complete
details.
Air may be drawn from a ventilated
crawl space or use an air duct.
The pedestal has an air
opening for use with the
outside air connections.
This allows air to be
drawn from behind the
pedestal.
Figure 7