HP (Hewlett-Packard) N2H3 Heat Pump User Manual


 
INSTALLATION INSTRUCTIONS 3-phase R-22 Split System Heat Pump
6 506 01 5001 00
C. ROUTING AND SUSPENDING REFRIGERANT
LINES
Run refrigerant lines as straight and direct as possible,
avoiding unnecessary bends and turns. Always insulate
the entire suction line. Both lines should be insulated
when routed through an attic or when routed through an
underground raceway.
When routing refrigerant lines through a foundation or
wall, do not allow refrigerant lines to come in direct
contact with the building structure. Make openings large
enough so that lines can be wrapped with extra insulation.
Fill all gaps with RTV caulk. This will prevent noise
transmission between the tubing and the foundation or
wall.
Along floor or ceiling joists, suspend refrigerant lines so
that they do not contact the building structure, water
pipes, or ductwork. Use insulated or suspension type
hangers. Metal straps must be at least 1” wide to avoid
cutting into the tube insulation. Keep the liquid and
suction lines separate. Refer to Figure 5.
Figure 5
Routing and Suspending Refrigerant Lines
INSULATION
SUCTION TUBE
LIQUID TUBE
OUTDOOR WALL INDOOR WALL
LIQUID TUBE
SUCTION TUBE
INSULATION
CAULK
HANGER STRAP
(AROUND SUCTION
TUBE ONLY)
JOIST
1” MIN
THROUGH THE WALL SUSPENSION
!
CAUTION
UNIT OPERATION HAZARD
Failure to follow this caution may result in improp‐
er product operation.
Do not bury more than 36” of line set underground.
Refrigerant may migrate to cooler buried section
during extended periods of unit shut-down, caus‐
ing refrigerant slugging and possible compressor
damage at start-up.
If ANY section of the line set is buried under‐
ground, provide a minimum 6” vertical rise at the
service valve.
D. OUTDOOR UNIT HIGHER THAN INDOOR UNIT
Proper oil return to the compressor should be maintained
with suction gas velocity. If velocities drop below 1500
fpm (feet per minute), oil return will be decreased. To
maintain suction gas velocity, do not upsize vertical
suction risers. Use the “<80 feet” suction line sizes shown
Figure 4.
Install oil traps every 20 feet of vertical suction line riser
(refer to Figure 6).
NOTE: If there is more than 20 feet vertical separation
between outdoor and indoor units, refer to the Long Line
Application Guidline document for additional instructions.
Figure 6
Oil Traps for Outdoor Unit Higher
than Indoor Coil
20 ft.
20 ft.
10” Max.
3” Min.
E. LIQUID LINE FILTER-DRIER
Outdoor units are shipped with an appropriate filter-drier
for installation in the liquid line. Leave the plugs in the tube
ends until the filter-drier is installed. The optimal location
for the filter-drier is close to the indoor coil. Heat pump
filter-driers are “bi-flow” type. Either end can be pointed
towards indoor coil. Refer to Figure 7.