Hearth and Home Technologies CD4842R Indoor Fireplace User Manual


 
Heatilator • Caliber CD Series • 4040-263 Rev N • 11/0844
Figure 10.8 Securing Vertical Pipe Sections
Figure 10.9 Securing Horizontal Pipe Sections
D. Secure the Vent Sections
Vertical runs of DVP pipe must be supported every 8 ft.
(2.44 m) after the 25 ft. (7.62 m) maximum unsupported
rise.
Vertical runs of SLP pipe must be supported every 8 ft.
(2.44 m).
Horizontal sections of vent must be supported every 5
ft. (1.52 m) with a vent support or plumber’s strap.
• Wall shield restops may be used to provide horizontal
support.
Vent support or plumber’s strap (spaced 120° apart)
may be used for support. See Figures 10.8 and 10.9.
• SLP ceiling restops have tabs that may be used to
provide vertical support.
WARNING! Risk of Fire, Explosion or Asphyxi-
ation! Improper support may allow vent to sag and
separate. Use vent run supports and connect vent
sections per installation instructions. DO NOT allow
vent to sag below connection point to appliance.
E. Disassemble Vent Sections
Rotate either section (see Figure 10.10) so the seams
on both pipe sections are aligned as shown in Figure
10.11.
Pull carefully to separate the pieces of pipe.
Figure 10.11 Align and Disassemble Vent Sections
Figure 10.10 Rotate Seams for Disassembly