Haier AU242AGERA Air Conditioner User Manual


 
1. Pressurize the equipment with nitrogen up to the design pressure and then judge the
equipment's air tightness, taking temperature variations into account.
2. When investigating leakage locations using a refrigerant, be sure to use R410A.
3. Ensure that R410A is in a liquid state when charging.
1. Use of oxygen as the pressurized gas may cause an explosion.
2. Charging with R410A gas will lead the composition of the remaining refrigerant in the
cylinder to change and this refrigerant can then not be used.
Read Before Installation
11
*The table shows the standards in Japan. Using this table as a reference, choose pipes that
meet the local standards.
Airtightness Test
No changes from the conventional method .Note that a refrigerant leakage detector for R22 or
R407C cannot detect R410A leakage.
3. Required accuracy of the vacuum gauge
Use a vacuum gauge that can measure up to 650Pa. Do not use a general gauge manifold
since it cannot measure a vacuum of 650Pa.
Halide torch
R22 or R407C leakage detector
NO
NO
Items to be strictly observed :
Vacuuming
Reasons :
1. Vacuum pump with check valve
A vacuum pump with a check valve is required to prevent the vacuum pump oil from flowing
back into the refrigerant circuit when the vacuum pump power is turned off (power failure).
It is also possible to attach a check valve to the actual vacuum pump afterwards.
2. Standard degree of vacuum for the vacuum pump
Use a pump which reaches 65Pa or below after 5 minutes of operation.
In addition, be sure to use a vacuum pump that has been properly maintained and oiled using
the specified oil. If the vacuum pump is not properly maintained, the degree of vacuum may
be too low.
4. Evacuating time
*Evacuate the equipment for 1 hour after 650Pa has been reached.
*After envacuating, leave the equipment for 1 hour and make sure the that vacuum is not lost.
5. Operating procedure when the vacuum pump is stopped
In order to prevent a backflow of the vacuum pump oil, open the relief valve on the vacuum
pump side or loosen the charge hose to drawn in air before stopping operation.
The same operating procedure should be used when using a vacuum pump with a check valve.