INSTALLATION
3. COMMISSIONING
3.1 Check there are no leaks in the water system and all internal parts are correctly fitted,
all seals are undamaged and the air controls and door catch are operating freely. The fit
of the door may be adjusted if required by moving the hinge blocks. This may be done
by loosening the hinge clamping nuts, and re-tightening when the correct fit is
achieved.
3.2 Carry out a final smoke draw test on the installed stove, by first warming the flue with a
blow-lamp, or similar, for about 10 minutes. Then place a smoke pellet in the stove,
with the air controls open, and close the door. Smoke should now be drawn up the flue
and be seen to discharge at the terminal. This test should be completed with all doors
and windows in the room where the stove is fitted closed. Should this test fail the
suitability of the flue system should be re-checked.
3.3 Light the stove and gently allow the temperature to increase slowly to operating levels.
Check that no combustion products are entering the room. When the stove has
reached a steady operating condition open the main firedoor and carry out a spillage
test with a smoke match or pellet around the door opening. If excessive spillage does
occur allow the stove to cool and re-check the suitability of the flue system.
3.4 Check heating system for correct operation and any leaks.
3.5 Explain the safe operation of the stove and the use of the controls to the user, along
with the need to only use suitable fuels. Also explain the cleaning and routine
maintenance requirements.
3.6 Explain the requirements to use a suitable fireguard when children, elderly or infirm
persons may be near the stove.
3.7
Record dealer/supplier details and installer details on page 2.
3.8 Record serial number on page 2.
3.9 Give this booklet to the customer.