STEP 5a: For through-the-oor water line and electrical
wires, mark another centerline 6 inches (152 mm) from
the back wall (g. 4).
STEP 5b: For through-the-wall water line and electrical
wires, mark a centerline 8 inches (203 mm) up from the
oor centerline (g. 5).
STEP 6: Make a 4-3/4 inch (121 mm) diameter hole (for
most oor anges) or a 5-1/8 inch (130 mm) diameter
hole (for swivel joint oor ange) at the centerline mark
furthest from the wall. Make a 1 inch (25 mm) hole at the
mark closer to the wall for the water line and electrical
wires (g. 6).
STEP 7: Insert oor ange into larger hole and secure
to the oor with #12x3/4-inch long at head wood or
sheet metal screws (g.7).
Fig. 5
Fig. 6
Fig. 4
IMPORTANT: The prefered installation method is to
mount the oor fIange directly on the nished oor.
However, if the bottom of oor ange and bottom of
china toilet must be mounted at different heights,
the oor ange must be mounted within 3/8 inch (10
mm) of the bottom of the toilet (see illustrations in
next column) or leakage will result.
Below-Floor Installation
STEP 8: Route 1/2-inch (13mm) PEX tubing through
the smaller hole and install a PEX 1/2-inch MPT tting
(g. 8).
NOTE: A water shut-off valve should be installed in the
water line to the toilet for maintenance requirements.
Fig. 7
Above-Floor Installation
Fig. 8