9
102989
INSTALLING
Continued
Continued
INSTALLATION AND CLEARANCES (Vent-Free Operation Only)
WARNING
Maintain the minimum clearances. If you can, provide greater clear-
ances from floor, ceiling, and adjoining wall.
Carefully follow the instructions below. This will ensure safe installation into a
masonry, U.L. listed manufactured fireplace, or vent-free firebox certified for use
with these log heaters.
Minimum Wall and Ceiling Clearances (see Figure 4)
A. Clearances from the side of the fireplace opening to any combustible wall
should not be less than 16 inches.
B. Clearances from the top of the fireplace opening to the ceiling should not be
less than 42 inches.
Figure 4 - Minimum Clearance to Wall and Ceiling
LOG SIZING REQUIREMENTS
Log Minimum Firebox Size
Size Height Depth Front Width
18" 17" 14" 20"
24" 17" 14" 26"
MINIMUM FIREPLACE CLEARANCE
TO COMBUSTIBLE MATERIALS
Log Size Side Wall Ceiling
18", 24" 16" 42"
42"
16"
Left and Right
Sides