Crown Boiler BSI103 Boiler User Manual


 
12
11
FIGURE 10: GAS CONNECTION TO BOILER
* State of Massachusetts Requires Manual
Shut-off Valve to be “T” Handle Type
*
VII Gas Piping
Gas piping to the boiler must be sized to deliver adequate gas for the boiler to fire at the nameplate input at a line pressure
between the minimum and maximum values shown on the rating plate. For more information on gas line sizing, consult the
utility or Chapter 2 of the National Fuel Gas Code.
Figure 10 shows typical gas piping connection to the BSI boiler. A sediment trap must be installed upstream of all gas
controls. Install a manual shut-off valve outside the jacket and ground joint union as shown.
The boiler and its gas connection must be leak tested before placing the boiler in operation. When doing this, the boiler
and its individual shut-off must be disconnected from the rest of the system during any pressure testing of that system at
pressures in excess of 1/2 psi. When pressure testing the gas system at pressures of 1/2 psi or less, isolate the boiler from the
gas supply system by closing its individual manual shut-off valve.