Bryan Boilers AH-FS151250D Boiler User Manual


 
BOILER FEED SYSTEM
DATE: 4/3/03
REP:2/1/99
8
2.2 OPERATING INSTRUCTIONS
CAUTION:
Check all electrical terminals and piping connections for tightness before start-up.
2.2.1 FAMILIARIZATION WITH MANUAL(S)
The user of the feed system and boiler system must familiarize himself with this manual to be sure
he is prepared to operate and maintain the system properly.
The operating instructions should be kept in a safe place and available to all who may be working
or operating the feed system.
READ THE MANUAL BEFORE ATTEMPTING A START-UP
2.2.2 TURNING THE SYSTEM ON
Make sure all valves are open that need to be open to the feed system in order to operate the
feed system. The tank should fill up to half full with make-up water and the valves to the pumps
on the suction end discharge side should also be opened and the strainers should be clean. The
pump should have been vented (if required) and all other instructions followed in this manual and
also in the manufacturer’s data manuals for each particular item supplied. When the tank has
been filled to at least half full and all other instructions followed, the feed system is ready for
operation. Power may be turned on to the system for operation. The boiler should also be
checked to make sure it is ready to receive water and is working properly.
2.3 MAINTENANCE SCHEDULE
Post a maintenance schedule in accordance with the recommendations in this manual. A typical
schedule is included in this manual.