Bosch Security Systems
| April 03 | 3922 988 97112 en
en
| 4
Digital Congress Network
| TCB 4 Upgrade Kit LBB 3519/20 | Chapter 1. Upgrade Kit LBB 3519/20
1.1 Before you Begin
WARNING:
Before performing any of the procedures described in this
document that require you to remove the top-cover of the CCU,
1. Before removing the top cover of the CCU, disconnect the mains supply and
remove the mains cable from its source and from the rear of the CCU.
2. Disconnect any peripherals connected to the CCU
3. The TCB4 upgrade interface card is shipped in antistatic packaging for protection
from electrostatic damage.
CAUTION:
Before unwrapping the antistatic packaging, ground yourself by
touching any unpainted metal surface on the Central Control Unit. This proce-
dure discharges static electricity that might harm the interface card.
REFERENCE:
If available refer also to Chapter 4 of the latest
edition of the DCN Installation and Operating Manual .
(Code No. 3922 988 433xx).
1.2 INSTALLING the TCB4 Interface card
1. Your upgrade kit includes:
- 1 x TCB4 interface card
- Interconnection (ribbon) cable terminated with a 9-pole D-type connector at one end
and a Micromatch connector at the other end.
NOTE:
If two ports are required, then an additional interconnection cable is also
required. This cable is ordered separately under Code no. 3922 156 24090,
through your local Bosch supplier.
Installation procedure
1.
Remove the top-cover from the CCU.
2. Locate the TCB (version 2 or 3). For location of the TCB see Fig 1-1.
NOTE:
For Multi-CCUs type LBB 3500/30 carefully remove the ‘Multi-CCU’
card from the TCB card. The TCB is located under the ‘Multi-CCU’ card.
3. Remove all interconnection cables from the TCB.
4. Remove the 6 screws securing the TCB,
5. Remove the TCB.
Once the TCB 2 or 3 is removed proceed as follows:
Minor modifications, (i.e. widening the holes to accommodate the 9-pole D-type
connector(s)) are required at the rear of the CCU. If the upgrade includes two Ports,
then an additional hole is required to accommodate Port 2.
1. Remove the TCB from its packaging (see 1.1 Before you Begin)
2. Position the TCB4 in place and secure using its 6 securing screws.
3. Position and secure the 9-pole D-type connector(s) in their modified hole(s).
4. With reference to FIGURE 1-1 and FIGURE 2-1 connect Port 1 and if applicable Port
2.
5. Connect the TCB4 to both 1/O control boards.
6. Double check connections according to FIGURE 1-1 and FIGURE 2-1.
1.3 SET-UP of the TCB4 Interface card
To ensure correct operation of the TCB4, the following settings are required:
1. DIP-switch S14 must be set, to configure the communication protocol and baud
rate used on Port 1 and Port 2 (see Chapter 3 ).
2. DIP-switch S9 must be set to configure the boards functionality (see Chapter 2.1 ).
3. Jumpers X13 and X14 must be set (see Chapter 2.2).
NOTE:
Once the TCB4 has been successfully installed in the CCU, replace the
top-cover and connect the mains supply to the CCU. Check the CCU for cor-
rect operation. If the CCU functions correctly, the CCU should be switched ON
for at least 24 hours to charge the back-up battery located on the TCB4.
Digital Congress Network
Installation and Operating Manual