![](https://pdfstore-manualsonline.prod.a.ki/pdfasset/5/b7/5b76f384-e349-4aae-a348-19debcadbefa/5b76f384-e349-4aae-a348-19debcadbefa-bg19.png)
930-110-01-B.00 PowerLogic
TM
EM4800 Series
04/2011 Installation
© 201
Schneider Electric All Rights Reserved
19
For a 600Y/347V or higher three-phase wye panel with potential
transformers with the 120V variant of the meter:
• Connect meter terminal A to the voltage disconnect phase A (red wire)
• Connect meter terminal B to the voltage disconnect phase B (black
wire)
• Connect meter terminal C to the voltage disconnect phase C (blue wire)
• Connect meter neutral terminal to neutral bar in the voltage disconnect
panel (white wire)
• Connect earth wire to earth post using lug provided
• Install power supply shorting jumpers (see Figure 10)
NOTE: For the wiring of the potential transformers, see Figure 5.
Figure 10: PowerLogic EM4800 meter 600Y/347V or higher three-phase
wye service with potential transformers connection
Legend:
1 BX cable
2 Earth
3 Phase C (blue)
4 Phase B (black)
5 Shorting jumper
6 Sense voltage terminal block (J3)
7 Neutral (white)
8 Phase A (red)
9 0.75-inch (1.9-cm) strain relief
8
4
7
5
6
2
1
3
9