Vulcan-Hart ML-052211 Boiler User Manual


 
– 21 –
6. Remove the two bolts from the pilot outage
protection valve and the bracket.
7. Disconnect the pilot outage protection valve
from the union and the thermostat.
8. Remove the pilot outage protection valve and
the ignitor wire from the broiler.
9. Reverse the procedure to install.
Thermostat (GHCB40)
WARNING: SHUT OFF THE GAS BEFORE
SERVICING.
WARNING: ALL GAS JOINTS DISTURBED
DURING SERVICING MUST BE CHECKED FOR
LEAKS. CHECK WITH SOAP AND WATER
SOLUTION (BUBBLES). DO NOT USE AN OPEN
FLAME.
1. Remove the control panel cover as outlined in
Covers, Panels and Handles.
2. Note the location and position of the
temperature probe in the oven.
3. Disconnect the thermostat from the pilot
outage protection valve and from the oven
burner tubing.
4. Remove the temperature probe from the oven.
5. Remove the thermostat with the temperature
probe from the broiler.