Samsung UM18A1C2 Air Conditioner User Manual


 
COMPLETING THE
INSTALLATION
Checking and Testing Operations
To complete the installation, perform the following checks and tests
to ensure that the air conditioner is operating correctly.
1 Review all the following elements in the installation:
Installation site strength
Piping connection tightness to detect any gas leakages
Connection wiring
Heat-resistant insulation of the piping
Drainage
Earthing wire connection
Correct operations (follow the steps below)
2 Press the On/Off button.
Result:
The indicator lights on the indoor unit flash at
half-second intervals.
While the indoor unit opens, the indoor unit fan runs
to start.
3 Press the button.
Result: The outdoor unit operates in cooling mode as starts.
4 Air flow direction Press the button one or more times to set the
blades to the 30° or 90° positions.
T
U
R
B
O
E-
43