INSTALLATION
INSTALLATION
Diagram 1
1) Frame in the enclosure for the unit with framing material. The framed
opening for the assembled kit is 42-1/2" high x 40-1/2" wide x 20-1/16"
deep (1080mm H x 1029mm W x 508mm D), see Diagram 1. Also
see Diagram 2 for corner installations.
Note: When constructing the framed opening, please ensure there
is access to install the gas lines when the unit is installed.
See diagram 3 for details.
2) For exterior walls, insulate the enclosure to the same degree as
the rest of the house, apply vapour barrier and drywall, as per local
installation codes. (Do not insulate the fi replace itself.)
3) The unit does not have to be completely enclosed in a chase. A non-
combustible header must be used. You must maintain clearances
from the vent to combustible materials: See "Clearances" section.
Combustible materials can be laid against the side and back standoffs
and the stove base.
FRAMING & FINISHING
The HeatWave Duct Kit has different
clearance and framing requirements,
check the HeatWave manual for details.
Diagram 2
Diagram 3
Note: Height is from the base of the unit. Take into consideration
the hearth height and material.