Mitsubishi Electronics PE-7MYC Air Conditioner User Manual


 
- 84 -
Canvas Duct
Canvas Duct
Duct earth
Duct earth
Duct
Duct
Outlet
Inlet
Duct-work length 850mm or more
Drain pan
Provide canvas flexible ducting between unit when connect to the duct-work.
The duct unit must use a nonflammable material.
Provide sufficient insulation for prevent dewdrop.
Duct construction
Lifting method
When the unit is to be lifted and moved, attach ropes to the suspension plates(3 p.c.s)
provided on the top of the unit.
When the unit is lifted, it 's center of gravity tends to shift the unit one side and so balance,
such as that in the figure below, should be attained.
The angles at which the ropes suspend the unit should be at least 60º at the compressor end
and at least 45º at the condenser end. Care should be taken to avoid contact with the main unit
while carrying.
It is necessary to protect the unit with the blanket so that the ropes should not injure the unit.
Hook (as directly aligned over
the center of gravity as possible.
PUH-15,20
(PU-15,20 is same method.)
MITSUBISHI
ELECTRIC
PUH-7,8,10 (upper blow)PUH-5,8,10 (side blow)