General Description
This unit is a high temperature hot water boiler. It consists of a non-pressure, vented water
compartment into which is installed an electric immersion heater thermostatically controlled through
a contactor relay, to keep the water always at the desired brewing temperature. Automatic refill
maintains water level in water compartment. All control system components are enclosed in a
stainless steel housing on the right end of the urn:
A master ON-OFF switch shuts off entire unit, including heater circuit: Separate low water cutoff
system protects heater and entire unit from damage.
Installation
1.
2.
3.
4.
5.
IMPORTANT TO ALLOW 6" CLEAR SPACE TO RIGHT ON CONTROL BOX FOR
ACCESS. Urn should be level, both front to back and left to right.
CONNECT WATER LINE. 3/8" NPT water inlet located at right end. Provide shutoff valve and
union in supply line near urn. Cold or hot water may be used, but hot water will give greater gal-
lon per hour capacity. We strongly recommend the use of copper or aluminum tubing to provide
flexibility and avoid strain on the unit. 3/8" O.D. Tubing is recommended.
CONNECT URN TO ELECTRIC POWER. Check to be sure that name plate marking of voltage
phase and number of wires matches supply lines. Remove cover on control housing. Terminal
block for line connections located in housing on right end. See drawing, as required. It is rec-
ommended that a fused disconnect switch be installed near urn. Urn body must be grounded
either through metallic conduit or else by means of ground wire. An experienced electrician
should be responsible for the installation of the unit, and its associated supply line. NOTE:
Neutral wire required on all single phase and on 208 volt 3 phase power supplies to operate
120volt AC control circuit. Do not replace cover until completion of installation.
FILL WATER COMPARTMENT. Turn on water supply and electric service to urn. Turn master
switch on. Do NOT turn on thermostat until water shows in gauge glass (approximately 6 min-
utes). When water shows, remove adhesive WARNING label from thermostat knob. Turn
thermostat knob maximum clockwise to BREW position. Pilot light over knob should light
showing heater power on. Water compartment will fill automatically to stop-full level, and should
reach operating temperature approximately 45 minutes later. When the pointer on thermometer
approaches the "W" in the blue BREW zone, unit is ready for operation.
REFILL RATE ADJUSTMENT. To gain maximum capacity of the boiler, and shorten heat
recovery time, adjust the water inlet flow regulator (located inside the control box) according
to the chart provided. Turning the threaded adjustment shaft clockwise increases the flow
rate, counterclockwise will decrease it.