commissioning
FIRST IGNITION OPERATION
1. Check the electrical supply.
Complete . . . . . . . . . . . . . . . . . . .
Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installer . . . . . . . . . . . . . . . . . . . . . . . . . .
2. Check the type of gas and
change the gas if necessary.
Complete . . . . . . . . . . . . . . . . . . .
3. Check the gas tightness.
Complete . . . . . . . . . . . . . . . . . . .
4. Measure the gas inlet.
Complete . . . . . . . . . . . . . . . . . . .
5. Check the Flue
Complete . . . . . . . . . . . . . . . . . . .
6. Fill the installation.
Complete . . . . . . . . . . . . . . . . . . .
7. Check the hydraulic water
tightness.
Complete . . . . . . . . . . . . . . . . . . .
8. Spin the pump.
Complete . . . . . . . . . . . . . . . . . . .
9. Purge the air with once
pressing on ESC button
during 5 sec.
Complete . . . . . . . . . . . . . . . . . . .
10. Set the heating power.
Complete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
11. Balance the central
heating circuit.
Complete . . . . . . . . . . . . . . . . . . .
12. Check the operation in
DHW mode.
Complete . . . . . . . . . . . . . . . . . . .
13. Adjust DHW  ow rate on
the boiler (if necessary).
Complete . . . . . . . . . . . . . . . . . . .
15. Check gas rate.
Complete . . . . . . . . . . . . . . . . . . .
14. Check combustion by
pressing the RESET button
for 5 sec.
Complete . . . . . . . . . . . . . . . . . . .
16. Check the ionisation
current.
Complete . . . . . . . . . . . . . . . . . . .
17. Explain to the end user the
working of the boiler.
Complete . . . . . . . . . . . . . . . . . . .