SEQUENCE OF THE IGNITION SYSTEM
Switch on the boiler as follows:
- Open the gas tap under the boiler by turning it
counterclockwise
- Turn on the general switch of the system and then, after lowering
the flap, turn the function selector to summer
, winter or
winter tank temperature
F
depending on the chosen operating
mode.
The boiler start to run according the automatic sequence: heat
request, fan start-up, tachometer check, ignition trials, gas
opening and ignition start-up.
Fig. 4